Commissioning in the freezing cold
Installed and started in the depths of winter, without an electric backup heater.
- Installed output
- 8 kW
- Configuration
- started at −12 °C
- Location
- Sălaj
- Year
- 2024
The problem
The old system failed in January. The house had no heating and the job could not wait until spring.
The challenge
Installing in freezing weather raises two problems: the system has to be filled and bled without any risk of freezing, and the pump starts straight away in the toughest conditions, with no gentle running-in period.
The solution
8 kW R290, commissioned at −12 °C. It took the load without an electric backup heater. The units are guaranteed down to −20 °C, so the start-up had a margin.